Anthropic-backed Queensland data centre clears federal environment hurdle
The A$32 billion Western Downs Digital Park still needs council and state approval, while a community group has raised concerns about the process.
By Quang Dinh

A proposed A$32 billion data centre backed by Anthropic has cleared a federal environmental hurdle, with the National Environmental Protection Agency deciding further assessment was unnecessary for the Queensland development.
The agency found the Western Downs Digital Park was unlikely to significantly affect matters of national environmental significance. Planned for a cattle feedlot 250 kilometres west of Brisbane, the project still requires approval at council and state levels.
The federal decision took two months. A Queensland Productivity Commission report put the average time for federal approvals in Queensland at more than three years. A government spokesperson attributed the speed to the project's design and choice of site, and said no public comments were received during the referral phase.
Anthropic signed an agreement for the hub in September and hoped to begin using it in 2027. Developer Zerra DC welcomed the decision, saying the location was chosen to limit community and environmental impacts while providing access to established energy infrastructure.
A Climate Council report identified the development as the data centre industry's largest potential polluter because of its electricity requirements. It found that, without renewable energy meeting its demand, the project would generate annual greenhouse emissions equivalent to those of 3 million cars by 2035.
Dalby residents have formed a group opposing the pace of development. Angela Prenzler, from Western Downs Says Pause, said she believed approvals were being fast-tracked across all levels of government.