Macquarie Point precinct cost reaches A$1.54 billion as state cap breaks

The stadium component is estimated at A$1.23 billion, with an undisclosed contingency excluded from the revised costs.

By Anjali Deshmukh

Published 2 min read

Construction machinery and building materials at a waterfront development site
Photo: ABC News

Tasmania will contribute more than its promised A$875 million limit towards Hobart's Macquarie Point stadium project, after the government put the precinct's estimated cost at A$1.54 billion.

The government's latest estimate puts stadium delivery at A$1.23 billion. The precinct's car park and power supply are budgeted at A$132 million, while a further A$183 million is for project delivery costs.

Those figures exclude an undisclosed client contingency intended to meet any further increases during final procurement negotiations. The September estimate of A$1.13 billion had included both contingencies and project costs.

Treasurer and Minister for Macquarie Point Urban Renewal Eric Abetz said state funds would meet the shortfall. The A$875 million contribution limit was among the commitments made to secure the Legislative Council votes needed for approval.

Abetz said the government would explore funding options to limit the borrowing required. Contributions from the federal government and AFL are A$240 million and A$15 million respectively.

Premier Jeremy Rockliff said higher oil, materials and labour costs, along with complexities associated with parliament's approval order, had driven the increase. He said discussions were under way with funding partners about increasing their contributions.

Rockliff ruled out seeking fresh parliamentary approval for the revised cost. Parliament has approved the roofed stadium with 23,000 seats, construction of which is required under Tasmania's AFL agreement.

Negotiations between the Macquarie Point Development Corporation and preferred tenderer BESIX Watpac are nearing completion, with the corporation hoping to sign the building contract by Christmas.

Corporation chief executive Anne Beach said value management had produced savings of about A$100 million. She said responsibility for some contractual risks would sit with the corporation and others with the builder.